**How to Relocate a TNB Electricity Meter (Meter Relocation)**

We provide TNB electricity meter relocation services for residential homes and commercial premises in a safe, legal manner and in accordance with TNB specifications. All processes are handled by Electrical Contractors registered with the Energy Commission (ST), including site inspection, document preparation, submission to TNB, until the work is completed and the electricity supply is reconnected.

6/12/20221 min read

1. Identify the Reason for Relocation
A TNB meter may be relocated for the following reasons:

Renovation works / kitchen, gate, or porch modification

Meter too close to wet or hazardous areas

Blocked access / safety concerns

Aesthetic requirements (external finishing)

2. Appoint a Registered Electrical Contractor
Meter relocation must be handled by:

Electrical Contractors registered with the Energy Commission (ST)

Contractors experienced in dealing with TNB

The contractor will:

Conduct a site inspection

Propose a new location in accordance with TNB specifications

Prepare drawings & supporting documents

3. Prepare the Required Documents
TNB usually requires:

Copy of the premises owner’s IC

Latest electricity bill

Land title / ownership documents / nearest neighbor’s electricity bill

Photos of the existing meter location & proposed new location

Application form (handled by the contractor)

4. Submit Application to TNB
Application is submitted through the TNB system by the contractor

TNB will review and conduct a site visit (if required)

Quotation / charges will be informed

5. Meter Relocation Works
After approval:

Electricity supply will be temporarily disconnected

Wiring works and meter relocation will be carried out

TNB will reconnect the supply and conduct verification

6. Supply Reconnection
Meter is reactivated at the new location

Safety testing is performed

Process completed

Estimated Timeframe
Approval & processing: 3 – 10 working days

On-site work: 1 day (depending on site conditions)