PERMOHONAN METER TNB – LULUS DULU BARU BAYAR - KONTRAKTOR ELEKTRIK BERDAFTAR - 0139214322
HOW TO APPLY FOR A NEW TNB METER AND PAYMENT CHARGES 2026 ACROSS MALAYSIA
HOW TO APPLY FOR A NEW TNB METER AND PAYMENT CHARGES 2026 ACROSS MALAYSIA
METER APPLICATION REQUIREMENTS
Before submitting an application, the house/premises must be fully completed or at least 90% completed and safe. Do not apply for a permanent meter if construction has not yet started or is still in early stages. For construction purposes, a temporary meter application is required.
Must comply with TNB meter installation specifications, with completed wiring, DB, and meter board installed according to TNB-specified standards.
Must not be located in a low-voltage constrained area. In some areas, TNB may not be able to provide supply due to insufficient available capacity.
Must have planning approval / local council licence / assessment tax for commercial applications in certain areas.
Make sure your application is under the correct category.
A New Meter Application / Newly Built is for premises that have never had a meter or do not have any TNB cable. If the premises previously had a meter, you must apply under Existing / Existing Meter.
A New / Newly Built application is mandatory to be processed through a contractor, which means only a contractor can submit the application and it cannot be done by the owner individually.
For new applications, there are 2 cost components that you need to pay:
Payment to TNB
i. Deposit / Security Deposit
ii. Consumer Connection Charge (CSP)
iii. Stamp Duty
(you may refer to the TNB price table that I have prepared according to house type)
Contractor management charges
TNB Meter Application Process
Site Visit – Document Submission – Submit – Approved – Payment – Installation – DONE
The process for a new meter application depends on the type of application.
EXPRESS
The express meter application process applies to overhead supply using up to 3 poles and is not located in a gazetted low-voltage area. It does not require a TNB officer site inspection before approval.
ESTIMATED
If the use of poles exceeds 4 poles or involves underground supply, the application must be submitted under estimated. This type of application requires a TNB officer to conduct a site visit before approval is granted. The processing time may be longer than an express application.
TNB Meter Installation Duration
The installation period for new applications is 1–14 days for express applications, and up to 21 days for estimated applications, or possibly longer.
This also depends on the location. Sometimes the process is faster, sometimes slower, depending on demand and site conditions.
The Consumer Connection Charge (CSP) must be paid to TNB after the application is approved, and the charges imposed depend on the scope of installation, whether it is overhead line (from pole to meter board) or underground line. For overhead lines, the pole cost is free and no additional pole charges are imposed by TNB. Applications for overhead and underground cables are priced differently.
Domestic / Residential
1 Phase
New – RM 450 (Overhead)
RM 1,700 (Underground)2 Domestic 3 Phase
New and upgrade – RM 750 (Overhead)
RM 1,700 (Underground)Commercial 1 Phase
New – RM 450
Commercial 3 Phase
New and upgrade – RM 1,700
The meter security deposit is also required to be paid to TNB after the electricity connection is completed by TNB. The deposit amount depends on the type of house, whether it uses a 1-phase or 3-phase meter, and for business premises, it depends on the maximum demand requirement. The deposit is refundable if the user closes the account.
Stamp duty RM10 — this usually means the stamped document falls under a fixed rate category (not based on cash value such as property sale and purchase).
TNB METER PAYMENT RATES – NEW APPLICATION
TNB payment rates can be referred to in the table below. Payments to TNB can be made directly to TNB without going through the contractor. Only the contractor’s service charges need to be paid directly to the contractor after approval. Our company is a registered electrical contractor under the Energy Commission (ST), CIDB, and TNB.
Note: The prices below are for new premises that have never had a meter. Contractor management charges are not included.
The consumer connection charge for underground supply is RM1,700, and the rate is the same for 1 phase and 3 phase.




Additional pole charges for TNB applications
At present, poles are provided free of charge, even if multiple poles are required, as long as they are needed for the meter application. The poles are the property of TNB, not individuals. TNB reserves the right to install poles if required, and not to install them if they are not necessary.
TNB Meter Application Contractor Charges
Single phase: RM 150 to RM 300
Three phase: RM 200 to RM 400
Therefore, the total price depends on the type of house and the number of supply phases required, as well as the distance and complexity of the application.
EXAMPLE: Kampung House – 1 Phase
Deposit: RM 170
Stamp Duty: RM 10
CSP: RM 450
Contractor Management Fee: RM 200
Total: RM 830 only
Contact me for more information on pricing: 013 921 4322 (BANI VENTURE)
www.wasap.my/60139214322
Lastly, applications differ by area depending on the documents and site requirements for TNB meter applications in each location.
Don’t worry, you may PM us for further information.
TNB Meter Application Procedure
TNB payment rates can be referred to in the table above. Payments to TNB can be made directly to TNB without going through the contractor. Only the contractor’s charges need to be paid directly to the contractor after approval. Our company is a registered electrical contractor under the Energy Commission (ST) and TNB.
Documents required to apply for a TNB meter under an INDIVIDUAL name
Proposed Address:
Phone No:
Email:
Location:
Applicant’s IC (marking for TNB / for TNB use)
Land document / land title / official search / S&P / agreement / assessment tax / any document that can be used as proof of ownership
Nearest neighbour’s electricity bill
Documents can be provided in PDF or image format, as long as they are clear.
If you know a TNB staff member, you may provide the staff ID to apply for a free deposit.
Documents required to apply for a TNB meter under a Company / Business name
Proposed Address:
Phone No:
Email:
Location:
Representative’s IC (marking for TNB / for TNB use)
Land document / land title / official search / S&P / agreement / assessment tax / any document that can be used as proof of ownership
Nearest neighbour’s electricity bill
SSM documents and Business Registration Certificate under the Registration of Businesses Act 1956 (Form D) and the Latest Business Profile Search issued by SSM, or Application for Registration of a Company (Section 14) and Notice of Registration (Section 15); or Company (Form 9);
or Certificate of Incorporation on Change of Company Name (Form 13) and Company Directors (Form 49); or certificate of registration for associations, cooperatives, or law firms
Documents can be submitted in PDF or image format, as long as they are clear.
If you know a TNB staff member, you may provide the staff ID to obtain a free deposit.


APPLY FOR TNB METER
TNB Meter Applications are divided into two categories:
Domestic (residential)
Commercial (business)




SUMMARY OF HOW TO APPLY FOR A TNB METER – NEW APPLICATION / NEWLY BUILT
New meter applications must be processed through a contractor.
Payment is required for deposit + connection charges + stamp duty + contractor charges, based on the type of premises as determined by TNB.TNB poles are provided free of charge, subject to the requirements of the premises / site.
The premises must be completed or at least 80% completed.
Installation period is 1–14 working days for express applications.
It is mandatory to deal with a contractor and submit all required documents to the contractor.
Providing Services
TNB Electricity Meter Applications for new and existing houses / projects / housing developments / shops
TNB Electricity Meter Applications for 1 Phase and 3 Phase
TNB Meter Name Change
TNB Electricity Meter Upgrade Applications
Temporary electricity supply applications
TNB meter upgrade works
Wiring and troubleshooting
Verification of construction approvals / Signing and stamping of electrical approvals for CF / G7
SERVING THE ENTIRE PENINSULAR MALAYSIA
APPROVAL FIRST, PAYMENT LATER | TRUSTED CONTRACTOR | BUMIPUTERA CONTRACTOR
THE CHOICE OF HOMEOWNERS, WIREMEN, BUILDING CONTRACTORS, AND DEVELOPERS
NO. 1 TNB METER APPLICATION CONTRACTOR IN MALAYSIA
For any enquiries, quotations, or suggestions, please contact:
Please call/WhatsApp: 013 921 4322
www.wasap.my/60139214322
We are a TNB-registered Electrical Contractor, registered with the Energy Commission (ST) and CIDB, offering TNB Meter Application services.
Experienced in handling TNB meter applications for houses, shops, factories, government premises, quarters, telco substations, farms, housing developments, projects, and offices.
Please WhatsApp us for enquiries regarding TNB meter installation.


For verification of registered contractors
Search: https://myaccount.mytnb.com.my/search/searchstcontractors


Excellent service, the TNB electricity meter application process was very fast.
Ali Rahman
Very satisfied with Bani Venture’s service. All TNB electricity meter applications were fully handled by Bani Venture.
Siti Aisyah